| Action | Deadline |
|---|---|
| Submit an outline field plan |
19th April 2013 |
| Request a map to aid Antarctic fieldwork planning (if required) | 31st March 2013 |
| Submit a Preliminary Environmental Impact Assessment form | 19th April 2013 |
| Check which permits are needed | 19th April 2013 |
| Submit Antarctic Permit applications (if required). The FCO are currently reviewing the permit application forms. It is likely that these will be ready by the end of June 2013. If you think you will require a permit, please contact the Antarctic Funding Office. |
Date TBC |
| Discuss arrangements for importing biological samples back to the UK | 24th May 2013 |
| Complete an Antarctic Research Project Risk Assessment and the BAS Chemical Approvals Register request |
24th May 2013 |
| Ensure any equipment is suited for Antarctic operations |
24th May 2013 |
| Discuss shipment of cargo to and from Antarctica |
24th May 2013 |
| Identify fieldwork personnel | 28th June 2013 |
| Ensure availability of fieldwork personnel for pre-deployment training | 28th June 2013 |